Construction Timeline

Site Survey is completed 10/21/2026

Pre Submission for Zoning and Permitting, In Process

Zoning and Permitting Submission - 1/1/2027 cost ~$70,000

Site Clearing and Infrastructure - 9/1/2027 Cost ~$800,000

Vertical Construction of Homes - 12/1/2027 Cost~$2,000,000

Vertical Construction of Community Center - 12/1/2027 Cost ~$500,000

Landscaping and Mini Farm Development- 5/1/2028 Cost ~$75,000

Professional Fees and Operating Income not included in these estimated costs.