Site Survey is completed 10/21/2026
Pre Submission for Zoning and Permitting, In Process
Zoning and Permitting Submission - 1/1/2027 cost ~$70,000
Site Clearing and Infrastructure - 9/1/2027 Cost ~$800,000
Vertical Construction of Homes - 12/1/2027 Cost~$2,000,000
Vertical Construction of Community Center - 12/1/2027 Cost ~$500,000
Landscaping and Mini Farm Development- 5/1/2028 Cost ~$75,000
Professional Fees and Operating Income not included in these estimated costs.